In PRINCE2, the Business Case is the North Star: it answers “Is this project still worth doing?” Because viability can drift, PRINCE2 mandates regular, event-driven checks—not a “set-and-forget” document.
Ownership Accountability
- Accountable: Executive (Project Board).
- Responsible for maintenance: Project Manager (on behalf of the Executive).
- Assurance: Senior User validates benefits; Senior Supplier validates feasibility/costs; Project Assurance challenges assumptions.
Minimum Cadence (PRINCE2-compliant)
- Project Initiation (PID approval):
Create/confirm the Business Case and Benefits Management Approach. - End of Every Stage (Managing a Stage Boundary):
Formal review and update before the next Stage Plan is approved. The Project Board re-confirms continued business justification. - Exception Situations (Exception Assessment):
Immediate review if forecast breaches tolerances (time/cost/quality/scope/benefit/risk). Approve an Exception Plan only if the updated case still stacks up. - Benefits Reviews (Post-Project):
Conduct benefits realization reviews per the Benefits Management Approach (e.g., T+3 months, T+6 months, T+12 months after go-live).
If nothing material changes within a stage, the Business Case can remain stable until the next end-stage review.
Materiality Thresholds (good practice):
- Cost: ±10% stage EAC variance or any change the project cost tolerance.
- Schedule: Slippage 10% of stage duration or impacts benefits window.
- Benefits: ≥5% downside to year-1 benefits or deferral of key benefit beyond payback horizon.
- Risk: Exposure (P×I) increases by one risk band (e.g., Medium → High).
- Scope: Change to MVP/critical product descriptions affecting benefits realization.
When a threshold is exceeded, update Business Case immediately and, if viability weakens, escalate to the Project Board.
What Exactly to Update
- Financials: Revised CAPEX/OPEX, NPV, IRR, Payback period.
- Assumptions Dependencies: New lead-times, vendor constraints, regulatory shifts.
- Benefits Profile: Timing, magnitude, measurability; confirm owners.
- Risk Exposure: Top threats/opportunities and mitigations; residual risk.
- Options Analysis: “Do nothing / Do minimum / Do something” comparison refreshed.
- Sensitivity Scenario Testing: Best/base/worst case with clear triggers.
Stage-by-Stage Playbook
Start-Up Initiation
- Draft outline Business Case → evolve to a full Business Case in the PID.
- Lock the Benefits Management Approach (who measures what and when).
Stage 1…N (Delivery Stages)
- During the stage: scan Highlight Reports; if thresholds trip, update now.
- End of stage: run End Stage Report + refreshed Business Case; Board decides “Continue / Change / Stop.”
Final Delivery Stage
- Confirm benefits that can be measured at project closure; schedule the rest post-project.
- Hand off the Benefits Management Approach to Operations/Benefits Owner.
Post-Project
- Execute benefits reviews on the agreed dates; update the Business Case record with actuals vs forecast; capture lessons.